Interiors & Office Fit-out — topic preview
Learn

Practitioner

Interiors & Office Fit-out

Ceilings, partitions, modular furniture and finish sequencing

5 lessons · 42 min · 4 videos · 0 articles

Lessons

A gypsum board false ceiling is a suspended grid of galvanised steel channels (usually a perimeter channel at the wall, intermediate channels and ceiling sections) hung from the slab soffit by adjustable hangers, with gypsum boards screw-fixed to the lowest layer of channel; the grid spacing, hanger spacing and board thickness are chosen to suit the span and the loads (light fixtures, AC diffusers, access panels) the ceiling must carry. Services — ducting, sprinkler pipes, cable trays, light boxes — are coordinated and fixed above the ceiling before boards are closed, because once boarded, every change becomes a cut-and-patch repair.

Gypsum partitions use a track-and-stud steel frame (similar principle to the ceiling grid, but vertical) with board fixed on both faces; cavity width accommodates services and insulation, and the partition height, stud spacing and board layers (single or double) are selected for the required fire rating and sound insulation where specified. A plain gypsum partition is not inherently fire-rated — fire-rated assemblies use specific board types, stud spacing and fixing patterns tested and certified as a complete system, and substituting any single component invalidates the rating.

Sequencing in a fit-out follows: services first-fix above ceiling and inside partition cavities, inspection and testing of concealed work, ceiling and partition boarding, taping and jointing of board joints to a flush finish, then painting, flooring and loose furniture. Skipping the inspection step before boarding is the most common cause of expensive rework in commercial fit-outs.

Remember on site

  • Suspended ceiling grids and partition frames are sized for span, hanger spacing and the loads/services they must carry.
  • Coordinate and inspect all concealed services before boards are closed — rework after boarding is expensive.
  • Fire-rated partitions are certified complete assemblies; substituting any component invalidates the rating.
  • Sequence is always: first-fix services → inspection → boarding → jointing → paint/flooring → furniture.

Check yourself

What must happen before gypsum ceiling boards are closed?

Is a standard gypsum partition automatically fire-rated?

What structural system typically supports a suspended gypsum ceiling?

Why is skipping the pre-boarding inspection step risky?

What determines gypsum partition cavity width?