Getting a building plan sanctioned is the first formal gate every project must pass through, and it starts with an architect preparing drawings that comply with the local Development Control Regulations (DCR) of the municipal corporation, development authority or panchayat having jurisdiction over the plot. These drawings are submitted, increasingly through an online portal in most cities, along with ownership documents, the latest property tax receipt, khata or revenue extract, and a structural stability certificate, after which the authority's town planning department scrutinises them against the permissible Floor Area Ratio (FAR), also called Floor Space Index (FSI), setbacks, height restrictions and parking norms before issuing the sanctioned plan.
FAR or FSI is the ratio of total permissible built-up area to the plot area, and it varies significantly by city, road width abutting the plot, and whether the project qualifies for incentives like Transfer of Development Rights (TDR) or premium FSI available in some states on payment of additional charges. Exceeding the sanctioned FAR, even by constructing an unauthorised extra floor, is one of the most common reasons for demolition notices and is treated very seriously by municipal authorities during inspection.
Setbacks are the mandatory open distances that must be left on all sides of the building from the plot boundary, and they exist for light, ventilation, fire tender access and future road widening, with exact distances varying by plot size, building height and local DCR. A frequent site-level mistake is to construct a compound wall or boundary structure that encroaches on the setback area, or to leave the setback on paper in the sanctioned drawing but build right up to the boundary in practice, both of which invite deviation notices during the final inspection before occupancy.
Once the sanctioned plan is approved and fees paid, the developer must apply separately for a Commencement Certificate (CC), which is the explicit authorisation to start construction, often issued in phases up to plinth level, then up to a certain number of floors, since many states require proof of basic infrastructure, like a sanctioned water connection or completed soil test, before each phase is released. Starting excavation or foundation work before the CC is issued, purely to save time, is a common but risky shortcut that can attract stop-work notices and penalties.
FAR/FSI basis
Varies by city/road width
CC release
Often phase-wise
Common violation
Setback encroachment
Remember on site
- Sanctioned plan approval checks compliance with DCR: FAR/FSI, setbacks, height and parking norms
- FAR/FSI varies by city, road width and incentive schemes like TDR or premium FSI
- Setbacks must be physically maintained on site, not just shown on the sanctioned drawing
- Commencement Certificate (CC) is the formal authorisation to start construction, often phase-wise
Check yourself
What does a sanctioned building plan confirm?
What does FAR/FSI represent?
What can increase the FSI available to a project in some states?
Why are setbacks mandated around a building?
What is a common site-level mistake regarding setbacks?
What is the Commencement Certificate (CC)?
What risk comes from starting excavation before the CC is issued?
What documents are typically submitted along with drawings for plan sanction?
Why does exceeding sanctioned FAR by building an extra floor attract serious action?
What influences the exact setback distance required for a plot?