Sign in to save & sync
Sign in

TBM segment rings

Rings and segments for a bored tunnel

Explanation in

Rings

0

rings

Segments
0 nos
Concrete per ring
0 m³ (0 ft³)
Total segment concrete
0 m³ (0 ft³)

How we got this

  1. 1

    Rings

    Formula
    L ÷ ring width
    Your numbers
    0 ÷ 0
    Answer
    0
  2. 2

    Per ring

    Formula
    π × (Do − t) × t × w
    Your numbers
    3.14 × (0 − 0) × 0 × 0
    Answer
    0 m³ (0 ft³)

The theory behind it

Method used: Length ÷ ring width

A TBM builds one ring after every push. Rings = length ÷ ring width; segments = rings × segments per ring. Concrete per ring = π × (Do − t) × t × ring width.

Assumptions used

  • •Metro tunnels: ring 1.2–1.5 m, 5+1 or 6+1 segments, 250–300 mm thick.

Codes & references

  • ITA WG2 — Guidelines for design of segmental tunnel linings
  • BTS Specification for tunnelling
History

Estimates for guidance only. Confirm quantities with your site engineer.