Random rubble stone masonry

Stone and mortar for RR masonry in foundations and walls

Explanation in

Stone

0

m³

Stone
0 m³ (0 ft³)
Wet mortar
0 m³ (0 ft³)
Cement
0 bags
Sand
0 m³ (0 ft³)

How we got this

  1. 1

    Stone

    Formula
    Volume × 1.25
    Your numbers
    0 × 1.25
    Answer
    0 m³ (0 ft³)
  2. 2

    Mortar

    Formula
    Volume × 0.35
    Your numbers
    0 × 0.35
    Answer
    0 m³ (0 ft³)
  3. 3

    Cement

    Formula
    Wet mortar × 1.33 ÷ (1+n) ÷ 0.0347
    Your numbers
    Answer
    0 bags

The theory behind it

Method used: Standard consumption per m³

Rubble stones are irregular, so about 1.25 m³ of loose stone and 0.35 m³ of wet mortar go into every 1 m³ of finished masonry.

Assumptions used

  • •Stone 1.25 m³ per m³ (incl. wastage); mortar 0.35 m³ wet per m³.

Codes & references

  • IS 1597 (Part 1) — Stone masonry
  • IS 1200 (Part 3)
History

Estimates for guidance only. Confirm quantities with your site engineer.