Stone and mortar for RR masonry in foundations and walls
- Stone
- 0 m³ (0 ft³)
- Wet mortar
- 0 m³ (0 ft³)
- Cement
- 0 bags
- Sand
- 0 m³ (0 ft³)
How we got this
1Stone
- Formula
- Volume × 1.25
- Your numbers
- 0 × 1.25
- Answer
- 0 m³ (0 ft³)
2Mortar
- Formula
- Volume × 0.35
- Your numbers
- 0 × 0.35
- Answer
- 0 m³ (0 ft³)
3Cement
- Formula
- Wet mortar × 1.33 ÷ (1+n) ÷ 0.0347
- Your numbers
- Answer
- 0 bags
The theory behind it
Method used: Standard consumption per m³
Rubble stones are irregular, so about 1.25 m³ of loose stone and 0.35 m³ of wet mortar go into every 1 m³ of finished masonry.
Assumptions used
- •Stone 1.25 m³ per m³ (incl. wastage); mortar 0.35 m³ wet per m³.
Codes & references
- IS 1597 (Part 1) — Stone masonry
- IS 1200 (Part 3)
Estimates for guidance only. Confirm quantities with your site engineer.