Sign in to save & sync
Sign in

Staircase

Step count from floor height, then concrete

Explanation in

Concrete Volume

0

m³

Number of steps
0 risers · 1 treads · exact riser 0 mm
Flights counted
1 nos (0 risers in all)
Waist slab
0 m³
Steps
0 m³
Stair length (slope, per flight)
0 m
Comfort (2R + T)
0 mm · steep
Cement
0 bags
Sand
0 m³
Aggregate
0 m³

How we got this

  1. 1

    Number of steps from the floor height

    Formula
    Risers n = Height ÷ Target riser (round) ; Exact riser = Height ÷ n
    Your numbers
    0 ÷ 0 = 0 → 0 risers of exactly 0 mm
    Answer
    0 risers · 1 treads (the upper floor slab is the last step) — counting the starting floor too gives 1 step surfaces, the "height ÷ riser + 1" way of saying the same stair
  2. 2

    Going and rise of the flight

    Formula
    Going = (n − 1) × Tread ; Rise = floor-to-floor height
    Your numbers
    (0 − 1) × 0
    Answer
    Going 0 m · Rise 0 m
  3. 3

    Sloping length of the waist slab

    Formula
    L = √(Going² + Rise²)
    Your numbers
    √(0² + 0²)
    Answer
    0 m
  4. 4

    Waist slab concrete

    Formula
    V₁ = L × Width × 0.15 m × No. of such flights
    Your numbers
    0 × 0 × 0.15 × 1
    Answer
    0 m³
  5. 5

    Step (triangle) concrete

    Formula
    V₂ = ½ × Tread × Exact riser × Width × n × No. of such flights
    Your numbers
    0.5 × 0 × 0 × 0 × 0 × 1
    Answer
    0 m³
  6. 6

    Total concrete

    Formula
    V = V₁ + V₂
    Your numbers
    0 + 0
    Answer
    0 m³
  7. 7

    Dry volume of concrete

    Formula
    Dry volume = Wet volume × 1.54
    Your numbers
    0 × 1.54
    Answer
    0 m³
    Why
    Dry ingredients bulk up; they lose ~54% volume once water is added and the mix is compacted.
  8. 8

    Cement (M20 = 1 : 1.5 : 3, sum of ratio 5.5)

    Formula
    Cement volume = Dry volume × 1 / 5.5 ; bags = volume / 0.0347
    Your numbers
    0 × 1/5.5 = 0 m³ ÷ 0.0347
    Answer
    0 bags (0 kg)
    Why
    One 50 kg bag of cement occupies 0.0347 m³ (density 1440 kg/m³).
  9. 9

    Sand (fine aggregate)

    Formula
    Sand = Dry volume × 1.5 / 5.5
    Your numbers
    0 × 1.5/5.5
    Answer
    0 m³

Short forms used above

M20
— Mix grade 20
M = Mix; 20 = 28-day cube strength 20 N/mm². Same logic for M15, M25, M30…
m³
— Cubic metre (volume)
kg/m³
— Kilograms per cubic metre (density)

The theory behind it

Method used: Floor-to-floor height divided by a target riser fixes the step count; waist slab plus triangular steps; IS 456 rise/tread limits

Enter the floor-to-floor height and a target riser — the number of steps is fixed by geometry, not guesswork: Steps = Height ÷ Riser, rounded to a whole number, and the exact riser is then Height ÷ Steps. A flight is a sloping waist slab carrying triangular steps. Concrete = sloping slab (going² + rise² by Pythagoras, × width × waist thickness) plus the steps, each a triangle of area ½ × tread × riser run across the width.

Assumptions used

  • •Risers = floor-to-floor height ÷ target riser, rounded; exact riser = height ÷ risers.
  • •Treads = risers − 1 — the upper floor slab is the final step. Counting the starting floor too gives 'height ÷ riser + 1' surfaces: the same stair, counted one step higher.
  • •Waist slab thickness 150 mm.
  • •Comfort rule: 2 × Riser + Tread ≈ 600–640 mm.
  • •Riser 150–175 mm and tread 250–300 mm for residential flights; NBC 2016 caps risers at 200 mm.
  • •Landing concrete is not included — add it as a separate slab.
  • •M20 grade, nominal mix 1 : 1.5 : 3 (cement : sand : aggregate).
  • •Dry-volume factor 1.54 on wet concrete volume.
  • •Cement bag = 50 kg = 0.0347 m³ (bulk density 1440 kg/m³).

Codes & references

  • IS 456:2000, Cl. 33 — Stairs
  • NBC 2016, Part 4 — Stair geometry and headroom
History

Estimates for guidance only. Confirm quantities with your site engineer.

© 2026 SiteMate. All rights reserved.