Ready-mix trucks & pour time

Transit mixers to order and how long the pour will take

Explanation in

Transit mixers

0

trucks

Order quantity
0 m³ (0 ft³)
Pour duration
0 hours
Truck every
—

How we got this

  1. 1

    Order

    Formula
    Volume × (1 + extra)
    Your numbers
    0 × 1
    Answer
    0 m³ (0 ft³)
  2. 2

    Trucks

    Formula
    Order ÷ capacity, rounded up
    Your numbers
    0 ÷ 0
    Answer
    0
  3. 3

    Time

    Formula
    Order ÷ placing rate
    Your numbers
    0 ÷ 0
    Answer
    0 h

The theory behind it

Method used: Order quantity ÷ mixer capacity

Order slightly more than the drawing volume to cover formwork bulging, uneven levels and spillage. The pour time tells you how many hours the gang, vibrators and lights are needed and helps plan cold joints.

Assumptions used

  • •Common mixers carry 6, 7 or 8 m³.
  • •Boom pumps place 20–40 m³/h on building slabs.

Codes & references

  • IS 4926:2003 — Ready-mixed concrete
History

Estimates for guidance only. Confirm quantities with your site engineer.