Sign in to save & sync
Sign in

Polymer repair mortar (spalls)

Bags of repair mortar for spalled concrete after rebar treatment

Explanation in

Bags

0

bags

Volume
0 m³ (0 ft³)
Mortar
0 kg (0 lb)

How we got this

  1. 1

    Volume

    Formula
    Area × depth
    Your numbers
    0 × 0
    Answer
    0 m³ (0 ft³)
  2. 2

    Weight

    Formula
    Volume × density × (1 + wastage)
    Your numbers
    0 × 0 × 1
    Answer
    0 kg (0 lb)
  3. 3

    Bags

    Formula
    kg ÷ bag
    Your numbers
    0 ÷ 0
    Answer
    0

The theory behind it

Method used: Volume × density

After breaking loose concrete, cleaning rusted bars and applying a rust passivator and bond coat, the cavity is rebuilt with a polymer-modified mortar in layers of 10–30 mm.

Assumptions used

  • •Typical density 1900–2200 kg/m³ as per manufacturer.

Codes & references

  • IS 13935:2009 — Repair & seismic strengthening
  • EN 1504-3 — Structural repair mortars
History

Estimates for guidance only. Confirm quantities with your site engineer.