Cement mortar for plaster
Cement
0
bags
Net plaster area
A = Length × Height × No. of faces + Ceiling − Openings
= 0 × 0 × 1 + 0 = 0 − 0
= 0 m²
Ceilings take a 6 mm coat on site — if you plaster one, run it separately with 6 mm thickness for an exact figure.
Wet mortar volume
V = Area × Thickness
= 0 m² × 0 mm (0 m)
= 0 m³
Dry volume
Dry = Wet × 1.27
= 0 × 1.27
= 0 m³
Voids in loose sand close up when the mortar is mixed and pressed on.
Cement (1:5, sum = 6)
Cement = Dry × 1/6 ÷ 0.035
= 0 × 1/6 = 0 ÷ 0.035
= 0 bags
Sand
Sand = Dry × 5/6
= 0 × 5/6
= 0 m³
Method used: Surface-area method with dry-volume factor 1.27 — IS 1661 plastering practice
Plaster is a thin layer of mortar: volume = area × thickness. That wet volume is increased by 27% to get the dry material, then split by the mix ratio. 12 mm is standard for internal walls, 15–20 mm for external, 6 mm for ceilings.
Estimates for guidance only. Confirm quantities with your site engineer.