Sign in to save & sync
Sign in

Excavation with side slopes

Pit or trench volume with battered sides, swell and truck loads

Explanation in

Excavation (in-situ)

0

m³

In-situ volume
0 m³ (0 ft³)
Loose volume to cart
0 m³ (0 ft³)
Top size
0 m (0 ft) × 0 m (0 ft)
Tipper loads
0 nos

How we got this

  1. 1

    Top dimensions

    Formula
    Top = bottom + 2 × slope × depth
    Your numbers
    0 + 2 × 0 × 0 and 0 + 2 × 0 × 0
    Answer
    0 × 0 m
  2. 2

    Areas

    Formula
    A1 = L×B, Am = mid-depth area, A2 = top area
    Your numbers
    0, 0, 0
    Answer
    m²
  3. 3

    Prismoidal volume

    Formula
    V = D/6 × (A1 + 4Am + A2)
    Your numbers
    0/6 × (0 + 4×0 + 0)
    Answer
    0 m³ (0 ft³)
  4. 4

    Loose volume

    Formula
    Loose = V × (1 + swell)
    Your numbers
    0 × 1
    Answer
    0 m³ (0 ft³)
    Why
    Soil bulks up once dug.
  5. 5

    Truck loads

    Formula
    Loads = loose ÷ tipper capacity (rounded up)
    Your numbers
    0 ÷ 0
    Answer
    0 loads

The theory behind it

Method used: Prismoidal formula

A pit with sloping sides is a frustum: the top is bigger than the bottom by twice the slope × depth on every side. The prismoidal formula (bottom + 4 × middle + top) × depth ÷ 6 gives the exact volume of such a shape. Dug soil loosens and occupies more space, so truck loads use the loose (swollen) volume.

Assumptions used

  • •Side slope is the same on all four sides. Use 0 for vertical (shored) sides.
  • •Swell: ordinary soil 20–30%, hard murrum 30–40%, rock 50–80%.
  • •Payment per IS 1200 Part 1 is on the undisturbed (in-situ) volume.

Codes & references

  • IS 1200 (Part 1) — Earthwork measurement
  • IS 3764 — Safety in excavation
History

Estimates for guidance only. Confirm quantities with your site engineer.