Pit or trench volume with battered sides, swell and truck loads
Excavation (in-situ)
0
m³
Top dimensions
Areas
Prismoidal volume
Loose volume
Truck loads
Method used: Prismoidal formula
A pit with sloping sides is a frustum: the top is bigger than the bottom by twice the slope × depth on every side. The prismoidal formula (bottom + 4 × middle + top) × depth ÷ 6 gives the exact volume of such a shape. Dug soil loosens and occupies more space, so truck loads use the loose (swollen) volume.
Estimates for guidance only. Confirm quantities with your site engineer.