Site levelling — cut & fill

Average-level method from four corner levels to a formation level

Explanation in

Cut volume

0

m³

Average ground level
0 m (0 ft)
Average cut depth
0 m (0 ft)
Cut volume
0 m³ (0 ft³)

How we got this

  1. 1

    Average level

    Formula
    (h1 + h2 + h3 + h4) ÷ 4
    Your numbers
    (0 + 0 + 0 + 0) ÷ 4
    Answer
    0 m (0 ft)
  2. 2

    Depth

    Formula
    Average − formation level
    Your numbers
    0 − 0
    Answer
    0 m (cut)
  3. 3

    Volume

    Formula
    |depth| × area
    Your numbers
    0 × 0
    Answer
    0 m³ (0 ft³)

The theory behind it

Method used: Average corner level (grid) method

For a plot that slopes fairly evenly, the average of the corner levels is the mean ground level. The difference between this mean and the required formation level, times the area, is the earth to cut (if ground is higher) or to fill (if lower).

Assumptions used

  • •Ground slopes roughly uniformly between corners. For uneven ground, split the plot into smaller squares and add them up.

Codes & references

  • IS 1200 (Part 1)
  • Standard surveying practice — grid levelling
History

Estimates for guidance only. Confirm quantities with your site engineer.