Column concrete
Width mm cm m in ft yd Depth mm cm m in ft yd Height mm cm m in ft yd No. of columns nos
Section 0 × 0 mm
Per column 0 m³
Cement 0 bags
Sand 0 m³
Aggregate 0 m³ How we got this 1 Cross-sectional area
Formula A = b × d Your numbers 0 × 0 Answer 0 m² 2 Volume of one column
Formula V₁ = A × Height Your numbers 0 × 0 Answer 0 m³ 3 Total concrete
Formula V = V₁ × No. of columns Your numbers 0 × 0 Answer 0 m³ 4 Dry volume of concrete
Formula Dry volume = Wet volume × 1.54 Your numbers 0 × 1.54 Answer 0 m³ Why Dry ingredients bulk up; they lose ~54% volume once water is added and the mix is compacted. 5 Cement (M20 = 1 : 1.5 : 3, sum of ratio 5.5)
Formula Cement volume = Dry volume × 1 / 5.5 ; bags = volume / 0.0347 Your numbers 0 × 1/5.5 = 0 m³ ÷ 0.0347 Answer 0 bags (0 kg) Why One 50 kg bag of cement occupies 0.0347 m³ (density 1440 kg/m³). 6 Sand (fine aggregate)
Formula Sand = Dry volume × 1.5 / 5.5 Your numbers 0 × 1.5/5.5 Answer 0 m³ 7 Coarse aggregate (20 mm)
Formula Aggregate = Dry volume × 3 / 5.5 Your numbers 0 × 3/5.5 Answer 0 m³ 8 Water (for W/C 0.5)
Formula Water = Cement weight × 0.50 Your numbers 0 × 0.50 Answer 0 litres Short forms used above
M20 — Mix grade 20 M = Mix; 20 = 28-day cube strength 20 N/mm². Same logic for M15, M25, M30…
W/C — Water–Cement ratio Weight of water ÷ weight of cement. Lower = stronger, if workable.
m³ — Cubic metre (volume)
kg/m³ — Kilograms per cubic metre (density) The theory behind it Method used: Limit-state axial load method — IS 456 Cl. 39.3 short-column capacity
Column concrete = cross-section × height. Height is measured from the top of the footing / floor slab to the soffit of the beam above; beam-column joints are counted once, with the beam.
Assumptions used • M20 grade, nominal mix 1 : 1.5 : 3 (cement : sand : aggregate). • Dry-volume factor 1.54 on wet concrete volume. • Cement bag = 50 kg = 0.0347 m³ (bulk density 1440 kg/m³). • Water-cement ratio 0.50; adjust for admixtures or site moisture. • No deduction for embedded reinforcement (usually < 1.5% of volume). • For reinforcement, use the Steel Quantity calculator or the full Bar Bending Schedule (BBS). • Height is clear height between slabs. Codes & references IS 456:2000 — Plain and Reinforced Concrete, Code of Practice IS 10262:2019 — Concrete Mix Proportioning Estimates for guidance only. Confirm quantities with your site engineer.