Pavement quality concrete, joints and dowel bars
PQC concrete
0
m³
PQC
Joints
Dowels
Method used: Slab volume + joints
Rigid pavements are PQC slabs (M40 flexural) on a Dry Lean Concrete base. Contraction joints are cut every 4.5 m to control cracking; dowel bars at 300 mm transfer load across them.
Estimates for guidance only. Confirm quantities with your site engineer.