Sign in to save & sync
Sign in

Box culvert / underpass

RCC box concrete for single or multi-cell boxes

Explanation in

Box concrete

0

m³

Outer size
0 m (0 ft) × 0 m (0 ft)
Section
0 m² (0 ft²)
Excavation (approx.)
0 m³ (0 ft³)

How we got this

  1. 1

    Outer width

    Formula
    n·W + (n+1)·t
    Your numbers
    0×0 + 1×0
    Answer
    0 m (0 ft)
  2. 2

    Section

    Formula
    Outer − openings
    Your numbers
    0×0 − 0×0×0
    Answer
    0 m² (0 ft²)
  3. 3

    Volume

    Formula
    Section × L
    Your numbers
    0 × 0
    Answer
    0 m³ (0 ft³)

The theory behind it

Method used: Gross section − openings

Overall width = cells × clear width + (cells + 1) × wall thickness; overall height = clear height + top + bottom slab. Concrete = (outer area − cell openings) × length.

Assumptions used

  • •Haunches ignored (add ~2–3%).

Codes & references

  • IRC SP 13 — Small bridges and culverts
  • IRC 112
History

Estimates for guidance only. Confirm quantities with your site engineer.