Loose soil needed to refill around foundations after compaction
Loose soil required
0
m³
Void to fill
Loose soil
Method used: Net void × compaction factor
Backfill fills the hole that is left after the footings, columns and PCC are built. Loose soil compacts in 150–200 mm layers and shrinks, so more loose soil must be brought than the void volume.
Estimates for guidance only. Confirm quantities with your site engineer.