Backfill & compaction

Loose soil needed to refill around foundations after compaction

Explanation in

Loose soil required

0

m³

Void to fill (compacted)
0 m³ (0 ft³)
Loose soil required
0 m³ (0 ft³)
Tipper loads
0 nos

How we got this

  1. 1

    Void to fill

    Formula
    Void = excavated − structure
    Your numbers
    0 − 0
    Answer
    0 m³ (0 ft³)
  2. 2

    Loose soil

    Formula
    Loose = void × (1 + compaction %)
    Your numbers
    0 × 1
    Answer
    0 m³ (0 ft³)

The theory behind it

Method used: Net void × compaction factor

Backfill fills the hole that is left after the footings, columns and PCC are built. Loose soil compacts in 150–200 mm layers and shrinks, so more loose soil must be brought than the void volume.

Assumptions used

  • •Compaction allowance 15–25% for well-rammed layers of 150–200 mm.
  • •Moisture at optimum while compacting.

Codes & references

  • IS 1200 (Part 1)
  • IS 2720 (Part 8) — Compaction
History

Estimates for guidance only. Confirm quantities with your site engineer.